Waste Exemption Changes in 2027

By James Roberts at TIPPA · Last reviewed

In short: England plans to end T8, T9 and U16 on 6 April 2027, if Parliament approves new rules due to start on 6 January 2027, when every exempt site starts keeping records of its waste. From 6 July 2027, exemptions connected to a permitted site end. Wales isn’t changing yet.

Have the 2027 Exemption Changes Been Approved?

Not yet. The draft regulations were laid before Parliament on 19 October 2026 and need a vote in each House, which hadn’t happened on 13 November 2026. GOV.UK expects approval before 17 December 2026. Until then the dates below are plans.

What Changes, and When?

England’s planned waste exemption changesTimeline, subject to Parliament approving the new rules: they start on 6 January 2027, when every exempt site starts keeping records of its waste and some waste codes change; T8, T9 and U16 end on 6 April 2027, so a permit is needed; on 6 July 2027 exemptions connected to a permitted site move into its permit, the lowest storage limit applies, and T4, T6, T12 and D7 meet their new conditions; U1, S1 and S2 meet theirs by 6 January 2028.6 January 2027SUBJECT TO PARLIAMENTNew rules start: every exempt site keeps recordsof its waste, and some waste codes change.6 April 2027T8, T9 and U16 end: a permit is needed. Apply beforethis date to keep working while it’s decided.6 July 2027Exemptions connected to a permitted site move intoits permit, and the lowest storage limit applies.T4, T6, T12 and D7 meet their new conditions.6 January 2028U1, S1 and S2 meet their new conditions.
England’s planned changes, if Parliament approves them.
  • 6 January 2027: the rules start. Every exempt site keeps records of its waste. A new registration gives the site’s postcode and grid reference, and the type and quantity of waste (regulation 11). The Environment Agency sets each exemption’s conditions from then, not the regulations (Defra).
  • 6 April 2027: T8, T9 and U16 end (what to do).
  • 6 July 2027: exemptions connected to a permitted site end, the lowest storage limit applies, and T4, T6, T12 and D7 meet their new conditions.
  • 22 July 2027: carrier permits begin, with exemptions of their own.
  • 6 January 2028: U1, S1 and S2 meet their new conditions.
Smaller Changes From 6 January 2027
  • Waste codes change in S3, T20, T21 and 20 others, to name the wastes more clearly.
  • T1 and U9 take only plastics without brominated flame retardants, or treated to remove them.
  • T11 takes printed circuit boards and power cables (16 02 15*), stored under a weatherproof cover.
  • D8 no longer takes pallets treated with methyl bromide.
  • The non-registered exemptions for storing waste at a site its producer controls or at a collection point (NWFD 3 and 4) go from 50 to 100 cubic metres.

Each is in the draft regulations’ Schedule; the waste codes are in Defra’s annex 7.

I Use T8, T9 or U16: What Do I Do?

Apply for an environmental permit before 6 April 2027, or stop that work on that date. Applied in time? You can keep working under the exemption until the permit’s decided.

  • Check whether a standard rules permit fits your site, or you need a bespoke one.
  • Registration expiring between 6 January and 6 April 2027? Renew it and apply for the permit, both before 6 April, and it carries on until the permit’s decided (regulation 20).
Scrap Metal, Tyres and Vehicle Parts
  • T9, recovering scrap metal: removed for its fire risk and the drainage and checks a metal site needs, so every metal recycler works under a permit (Defra).
  • T8, mechanically treating end-of-life tyres: removed for the fire risk of stored tyres. A tyre fitter, garage or recovery business that only stores its own waste tyres until they’re collected isn’t affected: that’s a non-registered exemption (Defra).
  • U16, using depolluted end-of-life vehicles for parts: removed for the illegal activity found under it (Defra).

What If My Exemption Is Beside a Permitted Site?

From 6 July 2027, an exemption at or next to a permitted waste site, and technically connected to what the permit allows, no longer counts as exempt.

  • Check whether yours is connected. The Environment Agency’s test is whether it adds to the permitted site’s risk: T6 chipping on land next to the site, beyond its boundary, does.
  • If it is, stop it or apply to bring it into the permit before 6 July 2027. Applied in time, you carry on until it’s decided (regulation 24).
  • Several exemptions on one site? From 6 July 2027 their storage limits for the same waste don’t add up: the lowest applies, whichever was registered first. Two allowing 500 tonnes of plastic and one allowing 300 allow 300 tonnes in all. Can’t stay within it? You need a permit.

What Records Must an Exempt Site Keep From 2027?

In England, from 6 January 2027, every exempt waste operation keeps chronological records of:

  • the quantity, type and origin of all the waste it takes;
  • how much product or material its recovery makes;
  • where relevant, where the waste goes, how often it’s collected, how it travels and how it’s treated.

Keep them for the registration and a year after, and send them to the Environment Agency electronically when it asks. Today only some exemptions, such as T9 and T12, must. Farms keeping U10 or U11 records under the nitrate rules are left out. Defra says the regulators will provide a form, which hasn’t been published.

What Changes for T4, T6, T12, D7, U1, S1 and S2?

New conditions, set by the Environment Agency: T4, T6, T12 and D7 by 6 July 2027, and U1, S1 and S2 by 6 January 2028 (GOV.UK). Until then each keeps its current conditions (today’s limits). The new ones haven’t been published.

Defra’s Plans for Each of the Seven

From Defra’s policy paper (July 2025), with the detail in its annexes:

  • T4, renamed “Preparatory treatment of waste”: lower storage limits and quicker turnover for some wastes, and conditions to cut the risk of fire.
  • T6, renamed “Treatment of waste wood and plant matter”: lower storage limits and quicker turnover.
  • T12: stricter conditions against waste being stockpiled and abandoned, and no mattresses.
  • D7, renamed “Burning vegetation at the site of production”: new storage times, and some wastes taken out.
  • U1, renamed “Use of wastes to construct and maintain surfaces and barriers”: wastes and amounts set for each kind of use, such as a track or a noise bund, in place of one overall limit.
  • S1 and S2: for secure storage before recovery elsewhere, and not allowed with a direct link to another exemption.

Is Wales Changing Too?

Not yet. England’s rules don’t reach Wales, Scotland or Northern Ireland. Natural Resources Wales says T8, T9 and U16 will go three months after a Welsh law comes into force, and the rest within 12 months. No date has been set: NRW will write to every holder. Scotland’s exemptions ended on 1 November 2026.

What Isn’t Settled Yet?

  • Parliament’s vote, expected before 17 December 2026.
  • The seven exemptions’ new conditions: when they’ll be published, and whether as Defra planned.
  • The records form: what it asks for, and in what format.
  • A permit refused: the exemption lasts until the application is decided, so a refusal ends it. Defra said the regulators would set out what happens to an incomplete or rejected application.
  • What counts as connected: Defra’s 2025 plans said the same operator, or shared staff or equipment; GOV.UK asks whether it adds to the permitted site’s risk. Which decides for an exempt yard beside a permitted site, run by the same people, taking different waste?
  • Wales’ date.

We’ve asked the Environment Agency and Natural Resources Wales, and we’ll update this guide when they answer.

Check the Official Guidance

Each rule above links to its source.

Sources: The 13 Official Pages This Guide Is Based On

How TIPPA Helps

  • Each load’s waste, weight and producer recorded as it’s received under your exemption, and where it goes when it leaves. Free.
  • Your exemption checked on its regulator’s register, with the waste codes it allows, and waste it doesn’t allow stopped. Free.
  • Its storage limits counted as loads come in, with a warning as you near one.
    Reporting add-on
  • A warning 30 days before it expires, and its renewal put in its place. Free.

TIPPA for exempt sites

Free for life. Pay only for the extras you choose.